Define Activities is the process of identifying the specific actions to be performed to produce the project deliverables.
Sequence Activities is the process of identifying and documenting relationships among the project activities.
Estimate Activity Resources is the process of estimating the type and quantity of material, people, equipment, or supplies required to perform each activity.
Estimate Activity Durations is the process of approximating the number of work periods needed to complete individual activities with estimated resources.
Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create a project schedule.