So easy to use!
Three-point estimates are based on determining three types of estimates: Optimistic, Most likely and Pessimistic.
* Most likely(M): The duration of the schedule activity, given the resources likely to be assigned, their productivity, realistic expectations of availability for the schedule activity, dependencies on other participants, and interruptions.
* Optimistic(O): The activity duration is based on a best-case scenario of what is described in the most likely estimate.
* Pessimistic(P): The activity duration is based on a worst-case scenario of what is described in the most likely estimate.
The PERT(Program Evaluation and Review Technique) analysis calculates E - Expected activity duration using a weighted average of these three estimates:
E = (O + 4M + P)/6
No comments:
Post a Comment